01 NCAC 30E .0303. POST OCCUPANCY EVALUATION
Latest version.
-
The designer evaluation process allows for a second evaluation to be conducted within 36 months of the completion of a capital project if design‑related latent defects are discovered. A separate procedure of the State Building Commission may require a formal post‑occupancy evaluation within 12 months of a building completion. The data from the 12 month post‑occupancy evaluation can be used as a substitute for the follow‑up designer evaluation if the Capital Projects Coordinator so determines.
History Note: Authority G.S. 143‑135.25; 143‑135.26;
Eff. October 1, 1988.