02 NCAC 59C .0404. WATER SUPPLY NEEDS  


Latest version.
  • (a)  State grants may cover up to fifty percent of non‑federal project costs, incurred to fulfill future and present water supply needs in conjunction with watershed improvement works, as follows:

    (1)           land rights acquisition costs as described in Rule .0402 of this Section; and

    (2)           all structural construction costs related to the development of water supply.

    (b)  State grants shall not cover nonstructural costs; for example, the costs of constructing pumps, pump stations, and pipe lines.

     

History Note:        Authority G.S. 106-840; 139‑4(d); 139‑54(3);

Eff. September 1, 1982;

Transferred from 15A NCAC 06C .0405 Eff. May 1, 2012.