15A NCAC 02D .1710. COMPLIANCE SCHEDULES  


Latest version.
  • (a)  Except as provided for in Paragraph (b) of this Rule, the schedule for compliance with the requirements of this Section shall meet the following deadlines:

    (1)           Each existing MSW landfill subject to this Section according to Rule .1702 of this Section and exceeding the design capacity limitation of Rule .1703(a)(1) of this Section shall submit an application for a permit under 15A NCAC 2Q .0500 by July 1, 1999.

    (2)           Each existing MSW landfill subject to this Section according to Rule .1702 of this Section and exceeding the design capacity and NMOC emission rate limitations of Rule .1703(a)(1) and (2) of this Section shall:

    (A)          submit a site-specific design plan for the gas collection and control system to the Director by July 1, 1999; and

    (B)          plan, award contracts, and install MSW landfill air emission collection and control system capable of meeting the emission standards established under Rule .1703 of this Section by January 1, 2001.

    (b)  For each existing MSW landfill subject to this Section as specified in Rule .1702 of this Section and meeting the design capacity condition of Rule .1703(a)(1) of this Section whose NMOC emission rate is less than 55 tons per year on July 1, 1998, shall:

    (1)           submit a site-specific design plan for the gas collection and control system to the Director within 12 months of first exceeding the NMOC emission rate of 55 tons per year; and

    (2)           plan, award contracts, and install MSW landfill air emission collection and control system capable of meeting the emission standards established under Rule .1703 of this Section within 30 months of the date when the conditions in Rule .1703(a)(2) of this Section are met.

     

History Note:        Authority G.S. 143-215.3(a)(1); 143-215.107(a)(4),(5);

Eff. July 1, 1998.