15A NCAC 02K .0213. CONSTRUCTION SCHEDULE  


Latest version.
  • The applicant shall submit a construction schedule that includes:

    (1)           Techniques and work force to be used to insure that the dam is constructed according to the plans and specifications;

    (2)           A construction schedule that includes the estimated time to complete the construction activities;

    (3)           Techniques to be used to divert the stream flow to prevent interference with construction and hazard to life, health, or property;

    (4)           The extent and method of quality control shall be subject to approval of the Director.

     

History Note:        Authority G.S. 143‑215.26; 143‑215.27; 143‑215.31;

Eff. June 15, 1980.