15A NCAC 02Q .0301. APPLICABILITY  


Latest version.
  • (a)  Except for the permit exemptions allowed under Rules .0102 and .0302 of this Subchapter, or as allowed under G.S. 143-215.108A, the owner or operator of a new, modified, or existing facility or source shall not begin construction or operation without first obtaining a construction and operation permit in accordance with the procedures under Section .0300; however, Title V facilities are subject to the Title V procedures under Section .0500 including the acid rain procedures under Section .0400 for Title IV sources.

    (b)  The owner or operator of a source required to have a permit under this Section may also be subject to the air toxic permit procedures under 15A NCAC 2Q .0700.

    (c)  The owner or operator of a source required to have a permit under this Section shall pay permit fees required under Section .0200 of this Subchapter.

     

History Note:        Authority G.S. 143‑215.3(a)(1); 143‑215.108;

Temporary Adoption Eff. March 8, 1994 for a period of 180 days or until the permanent rule becomes effective, whichever is sooner;

Eff. July 1, 1994;

Amended Eff. December 1, 2005; July 1, 1998.