15A NCAC 02Q .0311. PERMITTING OF FACILITIES AT MULTIPLE TEMPORARY SITES  


Latest version.
  • (a)  The Director may issue a single permit authorizing emissions from a facility or source at multiple temporary sites.

    (b)  Permits for facilities at multiple temporary sites shall include:

    (1)           the identification of each site;

    (2)           the conditions that will assure compliance with all applicable requirements at all approved sites;

    (3)           a requirement that the permittee notify the Division at least 10 days in advance of each change of site; and

    (4)           the conditions that assure compliance with all other provisions of this Section.

     

History Note:        Filed as a Temporary Adoption Eff. March 8, 1994 for a period of 180 days or until the permanent

rule becomes effective, whichever is sooner;

Authority G.S. 143‑215.3(a)(1); 143‑215.108;

Eff. July 1, 1994;

Amended Eff. July 1, 1996.