15A NCAC 02Q .0313. EXPEDITED APPLICATION PROCESSING SCHEDULE
-
(a) Using the procedures contained in this Rule may result in a permit that EPA does not recognize as a valid permit.
(b) An applicant may file an application to follow the expedited review for application certified by a professional engineer as set out in G.S. 143-215.108(h) if:
(1) The applicant specifically requests that the permit application be processed under the procedures in G.S. 143-215.108(h); and
(2) The applicant submits:
(A) applications as required under Rules .0304 and .0305 of this Section;
(B) a completeness checklist showing that the permit application is complete;
(C) a draft permit;
(D) any required dispersion modeling;
(E) a certification signed by a professional engineer registered in North Carolina certifying the accuracy and completeness of draft permit and the application, including emissions estimates, applicable standards and requirements, and process specifications;
(F) a consistency determination as required under Rule .0304(b)(1) of this Section;
(G) a written description of current and projected plans to reduce the emissions of air contaminants as required under Rule .0304(b)(2) of this Section;
(H) a financial qualification if required;
(I) substantial compliance statement if required; and
(J) the application fee as required under Section .0200 of this Subchapter.
(c) The applicant shall use the official application forms provided by the Division or a facsimile thereof.
(d) The Division shall provide the applicant a checklist of all items of information required to prepare a complete permit application. This checklist shall be the checklist used by the Division to determine if the application is complete.
(e) The Division shall provide the applicant a list of permit conditions and terms to include in the draft permit.
(f) Before filing a permit application that includes dispersion modeling analysis submitted in support of the application, the applicant shall submit a modeling protocol and receive approval for the dispersion modeling protocol.
(g) The Division shall follow the procedures set out in G.S. 143-215.108(h) when processing applications filed in accordance with this Rule.
History Note: Authority G.S. 143-215.3(a)(1); 143-215.108;
Eff. July 1, 1998.