15A NCAC 02Q .0313. EXPEDITED APPLICATION PROCESSING SCHEDULE  


Latest version.
  • (a)  Using the procedures contained in this Rule may result in a permit that EPA does not recognize as a valid permit.

    (b)  An applicant may file an application to follow the expedited review for application certified by a professional engineer as set out in G.S. 143-215.108(h) if:

    (1)           The applicant specifically requests that the permit application be processed under the procedures in G.S. 143-215.108(h); and

    (2)           The applicant submits:

    (A)          applications as required under Rules .0304 and .0305 of this Section;

    (B)          a completeness checklist showing that the permit application is complete;

    (C)          a draft permit;

    (D)          any required dispersion modeling;

    (E)           a certification signed by a professional engineer registered in North Carolina certifying the accuracy and completeness of draft permit and the application, including emissions estimates, applicable standards and requirements, and process specifications;

    (F)           a consistency determination as required under Rule .0304(b)(1) of this Section;

    (G)          a written description of current and projected plans to reduce the emissions of air contaminants as required under Rule .0304(b)(2) of this Section;

    (H)          a financial qualification if required;

    (I)            substantial compliance statement if required; and

    (J)            the application fee as required under Section .0200 of this Subchapter.

    (c)  The applicant shall use the official application forms provided by the Division or a facsimile thereof.

    (d)  The Division shall provide the applicant a checklist of all items of information required to prepare a complete permit application.  This checklist shall be the checklist used by the Division to determine if the application is complete.

    (e)  The Division shall provide the applicant a list of permit conditions and terms to include in the draft permit.

    (f)  Before filing a permit application that includes dispersion modeling analysis submitted in support of the application, the applicant shall submit a modeling protocol and receive approval for the dispersion modeling protocol.

    (g)  The Division shall follow the procedures set out in G.S. 143-215.108(h) when processing applications filed in accordance with this Rule.

     

History Note:        Authority G.S. 143-215.3(a)(1); 143-215.108;

Eff. July 1, 1998.