15A NCAC 02Q .0513. PERMIT RENEWAL AND EXPIRATION  


Latest version.
  • (a)  Permits being renewed are subject to the procedural requirements of this Section, including those for public participation and affected State and EPA review.

    (b)  Permit expiration terminates the facility's right to operate unless a complete renewal application has been submitted at least nine months before the date of permit expiration.

    (c)  If the permittee or applicant has complied with Rule .0512(b)(1) of this Section, the existing permit shall not expire until the renewal permit has been issued or denied.  All terms and conditions of the existing permit shall remain in effect until the renewal permit has been issued or denied.

     

History Note:        Filed as a Temporary Adoption Eff. March 8, 1994 for a period of 180 days or until the permanent

rule becomes effective, whichever is sooner;

Authority 143‑215.3(a)(1); 143‑215.107(a)(10); 143‑215.108;

Eff. July 1, 1994.