(a) Approval of a sedimentation and erosion control plan will be contained in a document called "Certificate of Plan Approval" to be issued by the Commission.
(b) The Certificate of Plan Approval must be posted at the primary entrance of the job site before construction begins.
(c) No person may initiate a land-disturbing activity until notifying the agency that issued the Plan Approval of the date that the land-disturbing activity will begin.
History Note: Filed as a Temporary Rule Eff. November 1, 1990, for a period of 180 days to expire on April 29, 1991;
Authority G.S. 113A‑54(b);
ARRC Objection Lodged November 14, 1990;
ARRC Objection Removed December 20, 1990;
Eff. January 1, 1991;
Amended Eff. July 1, 2000.